Road Improvement Plan
Road Improvement Program Updates
2010 Road Improvement Program
Construction activities for the 2010 Road Improvement Program are complete
with only punch list items (restoration, spot repairs, etc.) to be remedied this
Spring, weather permitting.
2011 Road Improvement Program
Conge Drive has been selected to be reconstructed for this year’s program.
Bids have been received and a Contractor has been selected. Construction is
scheduled to begin mid-May and will continue through mid-July. Work includes:
- Water main replacements along Conge Drive
- Road Reconstruction on Conge Drive and at the intersection of Kensington
Road and Trowbridge Court
Intermittent lane closures on Kensington Road should be expected during this
construction timeframe, please use alternate routes when possible.
2012 Road Improvement Program
The City Commission has approved the rehabilitation of Epping Lane.
Topographic survey and design is anticipated to begin in the Fall of 2011 for
construction in 2012.
For more information, please contact the City office at: 248-544-1420.
2010 Road Program Open House Presentation
2010 - 2012 Road Improvement Plan - Final
Map A - all of the City’s roads
and their current conditions. The road conditions are ranked
from Good-Poor.
Map B - all of the City’s roads
and their current conditions with all necessary water,
sewer, and culvert improvements.
Map C - all the roads to be
addressed in 2010 – 2012 with the associated water, sewer,
and bridge/culvert improvements.
The Letter to City Commission presenting the report and its
findings
The Draft Road Report Presentation to City Commission
The Public Information Meeting Presentation from August 5,
2009
The Letter to City Commission recommending final approval of
the updated 2010-2012 Road Program Report
|