July 18, 2019

Dear Country Club Residents:

Due to the high temperatures expected on Friday, July 19th, the driveway paving work must be rescheduled. Operating the paving equipment on the newly paved road in the high temperatures will cause damage to the road. Completing the driveway pavement in the extreme heat can also cause difficulty for the pavement to be laid properly.

To help residents with driveway access while waiting for the driveway pavement to be completed, the contractor will be placing a gravel base for every residence at one of your driveway access points. This is expected to be done today, July 18th.

As soon as we have confirmation when the driveway paving work can be safely completed, we will send another message with the paving schedule for next week.

Onsite Field Representative Dave David (248) 535 3399
Project Engineer Lia Michaels (586) 634-6211


Copyright © 2016 City of Bloomfield Hills. All Rights Reserved.
45 E Long Lake Road, Bloomfield Hills, MI 48304